According to BHEL, this agreement represents an advancement in India's
The contract, signed on Sunday (August 25), encompasses the supply of critical equipment and the supervision of the erection and commissioning processes for three major
Each project will feature a capacity of 2x800 MW and will be based on advanced
Under this agreement, BHEL is tasked with providing a comprehensive suite of equipment, including Boilers, Turbines, Generators, and associated auxiliaries.
The contract also includes control and instrumentation systems. In addition, BHEL will oversee the installation and commissioning of these systems, ensuring that the projects meet all operational and performance standards.
The timeline for project completion varies across the different locations. The Kawai Phase-II project is expected to be completed within 49 months, Kawai Phase-III within 52 months, and Mahan Phase-III within 55 months.
These timelines reflect the scale and complexity of the projects and the commitment to delivering them within a specified period.