NTPC completes trial of Khargone Super Thermal Power Project's second unit
"Second unit of 660 MW of Khargone Super Thermal Power Project has been added to installed capacity of NTPC on successful completion of trial operation," NTPC said in a BSE filing.
With the addition, the total installed capacity of NTPC and NTPC group has become 50,355 MW and 58,816 MW, respectively.
On January 31, NTPC announced commercial operation of the power plant's unit-1 of 660 MW with effect from February 1. ABI HRS